(A) Conditional use permits become effective seven (7) days after approval by the planning and zoning commission, but in the event an appeal is filed, said permit shall not become effective until a decision upholding granting of the permit is arrived at by the council.

(B) The construction of any improvements allowed by a conditional use permit shall commence within twelve (12) months or as otherwise stipulated by the commission and must be completed within eighteen (18) months or as otherwise stipulated by the commission in accordance with the development plan, unless extended by the planning and zoning commission, otherwise the conditional use permit shall become null and void.

(C) The commission may establish a time limitation for specific conditional use permits and prior to the termination of this time limit, the commission may reconsider said use permit to determine if the permit should be reissued for an additional time period or be terminated.

(D) A conditional use permit shall not be effective until the conditions of the permit are fulfilled unless specific clarifications on the conditional use permit as to timing of compliance are present.

(E) If a time limit is not established by the commission, and the conditional use is discontinued for more than twelve (12) months, a new conditional use permit shall be required.

(F) An applicant may submit a master plan of a proposed development which requires a conditional use permit and have the development approved by the commission. No further conditional use permit process will be necessary to implement this plan as long as it is in substantial compliance with the master plan and is completed within the time period established by the commission.

(G) No person shall reapply for the same or substantially the same use permit on the same or substantially the same plot, lot, or parcel of land within a period of one (1) year from the date of denial or revocation of said use permit. (Ord. No. 473, §§ 1 – 4, 6-6-00; Ord. No. 2006-07, § 3, 3-7-06; Ord. No. 2007-03, § 1, 1-16-07; Ord. No. 2009-08, §§ 1, 2, 6-2-09. 1976 Code § 15-1-32(I))